Representative projects:
|
|
|
|
|
|
| |
|
|
Hurghada-Luxor Railway
Determination of the most favorable route based on a topographic study of the maps published by the Egyptian Surveying Authority (ESA), determination of the separation points at the beginning and end of the line and the proposed location and plans of crossing points, as well as preparation of horizontal and vertical sections of the suggested routes.
|
|
|
|
Container Berth Dekhaila Port (B100) (Egypt)
Complete survey of offshore 1.5km breakwater. Precise modeling of slopes and complete shape of the berth was produced.
|
|
|
|
City of Idku Strategic and Detailed Plan
We conducted a detailed survey of the areas north of the existing city (450 hectares) to produce base maps for a strategic and detailed urban plan of the area. The site included existing 'random' roads and buildings in a congested environment.
|
|
|
|
Shobra Banha Freeway
A topographic survey of the 40 km suggested route for a new freeway to connect the Cairo Ring Road and the Cairo-Alexandria Agricultural Road. The survey included the establishment of 18 GPS control points and 70 additional total control stations using ground surveying techniques. All features within a 500m buffer on each side were surveyed and necessary maps were produced.
|
|
|
|
Drinking Water & Sanitary Projects in Upper Egypt
A survey was conducted to provide details of roads and surrounding buildings of the villages of Derau, Edfu, Kom-Ombo-Aswan, Egypt (area of 1100 hectares) to serve as base maps for the design of drinking water and sanitary networks in the villages. The scope included the establishment of longitudinal and cross sections as needed and the survey of buildings and utilities.
|
|
|
|
Sana'a University Campus (Yemen)
GIS data collection at
the existing site, topographic survey and geotechnical investigation of 830 acres,
design of the master plan for the university campus until 2023, and design of the
campus buildings and infrastructure.
|
|
|
|
LNG Project at Damietta Port (Egypt)
Geotechnical investigation and
topographic survey of the project site (530 acres), which consists of a LNG plant,
large diameter reinforced concrete LNG storage tanks, pipelines, and roads, and
provision of construction testing and technical services, including site laboratory
equipment and quality control staff.
|
|
|
|
Assiut Barrage (Egypt)
A full study of the site, including
geotechnical investigation and testing, topographic and bathymetric surveys, groundwater
modeling, and an environmental assessment to determine whether rehabilitation of
the current barrage or construction of a new one would be the most viable.
|
|
|
|
Khalphout Port (Yemen)
GPS vertical and horizontal
control points were established and a topographic survey of the seabed (to depths
of 16m) using echo sounding and Real-time Kinematic (GPS) was conducted, along with
a
topographic survey of the onshore site area to determine the design of the new port.
|
|
|
|
Sidi Krir Harbour (Alexandria, Egypt )
Hydrographic work included surveying
the sea bottom in the site area to produce detailed contour maps, and a topographic
survey of the shoreline and surrounding area, including a cadastral survey.
|
|
|
|
El Gouna Marina (Red Sea, Egypt)
Our survey work included topographical
and cadastral surveys to update the site data, man-made shoreline changes, power
lines, water supply networks, and current land uses in the area. Detailed leveling
was determined using grid and spot leveling, and horizontal and vertical control
was performed to link the different facilities on the land area to the same coordinate
system.
|
|
|
|
Zowaytena & Oqihal Fishing Ports (Libya)
Geotechnical investigation and
topographic and hydrographic surveys to design the master plans for the ports and
detailed designs of the port buildings, facilities, and infrastructure. Also, hydraulic
studies and designs for the breakwaters, quay walls, and other port elements.
|
|
|
|
Suez Canal Bridge Feasibility Study (Egypt)
Detailed topographic surveys
performed at four potential locations for the bridge, with full cadastral survey
of all existing features and preparation of contour maps using grid and spot leveling.
Horizontal and vertical controls were used to tie the survey works to the national
geodetic network and benchmarks.
|
|
|
|
|
|